[jbosstools-dev] ACTION REQUIRED: Preparing for 4.2.3.CR1 CF next week [Mar 12]

Alexey Kazakov akazakov at exadel.com
Thu Mar 5 20:41:08 EST 2015


I updated the parent pom for base and server. We will probably change 
javaee and hibernate too. We will update the parent pom for them when 
merging those changes.

On 03/05/2015 11:49 AM, Nick Boldt wrote:
> Some steps need to be done to get ready for code freeze next week (March
> 12).
>
> These are:
>
> a) rename/rebuild parent pom, upversioned to 4.2.3.CR1 [done]
> b) rename/rebuild target platform
> c) update projects *which will have changes for CR1* to use this latest
> parent pom
>
> Rather than asking *everyone* to update their root pom and wasting your
> time w/ Task JIRAs, I'd rather ask this:
>
> * Which projects plan to contribute changes to 4.2.3.CR1?
>
> If you have changes, please upversion your parent pom to use
> 4.2.3.CR1-SNAPSHOT.
>
> If you do not, you need do nothing at this time.
>
> If you would still like a Task JIRA next week, I can certainly create
> them. Just let me know which project(s) need them and I'll skip sending
> them to those who don't need them.
>
>