Due to meetings and public holidays 2.4.0.CR1 will be delayed and will be
released on Monday 21st. Then 2.4.0.Final is on Wednesday 23rd.

We will follow-up with 2.4.1.Final on 7th December.

All changes for 2.4.0 needs to be in by end of Friday 18th December. Marek
will drive testing of the release on Monday 21st. The release will be done
in the evening (EU time) on Monday 21st.

Remaining work for 2.4.0.CR1 includes:

* LDAP porting to User Storage SPI including migration. If not ready it'll
get postponed to 2.4.1.
* Infinispan cache issues - Marek is working on this and the aim is to
include. If not ready it'll get postponed to 2.4.1.
* Remove native libraries included in SSSD jar - Bruno is working on this.
* Fuse issues - Marek is on these
* A few more minor issues, see JIRA for list

Postponed to 2.4.1:

* Kerberos and SSSD porting to User Storage SPI
* LDAP without syncing users to Keycloak db
* Removal of old User Federation SPI