[weld-dev] Weld 1.0.0 release schedule

Ondřej Skutka oskutka at redhat.com
Mon Nov 9 06:58:51 EST 2009


On Sat, 2009-11-07 at 19:23 +0000, Pete Muir wrote: 
> Hi all,
> 
> In the next few days we have both the code freeze for GlassFish V3  
> (Monday 9th November) and the submission of the final draft of JSR-299  
> (on Wednesday 11th November). We are going to *try* to use the same  
> release (1.0.0) artifacts for both events (as otherwise I will get  
> *no* sleep at all ;-). With this in mind, the schedule is as follows:
> 
> * Sunday 8th: Code freeze for API project and release CDI API and Weld  
> SPI 1.0.
>     - Gavin, this means any changes you want for the 1.0 JavaDoc need  
> to be in by tomorrow morning. Please tell me if this won't happen.
> 
> * Sunday 8th: Code freeze for CDI TCK and release 1.0.0.CR7
>     - Everyone, please let me know if you have any major outstanding  
> commits or issues with the TCK asap
>     - Jozef, I haven't seen any commits for the interceptors spec,  
> what is your status?
>     - Shane, please confirm the TCK has been updated to the latest  
> spec that Gavin has sent out
> 
> * Sunday 8th: Code freeze for Weld core, and *hopefully* release 1.0.0  
> (this is contingent on me not running out of time, otherwise I will  
> continue on Monday)
>     - Marius, Roger, can you ping me and we can discuss whether to  
> slip your remaining issues
>     - this release will use the 1.0 version of the API and the  
> 1.0.0.CR7 version of the TCK [1]
> 
> * Monday 9th: GlassFish code freeze
> 
> * Monday 9th: Ongoing work on TCK and ref docs, and on getting  
> examples, Servlet, Wicket and SE integration code passing all tests  
> and working
> 
> * Tuesday 10th: Code freeze for example, ref docs, Servlet, Wicket and  
> SE integration code and release.
> 
> * Tuesday 10th: Code freeze and release of TCK 1.0.0
>     - We will run this against Weld 1.0.0 and verify that we still pass
>     - Before tagging, we will update the assertions and tests to be  
> marked 1.0.FD
> 
> * Tuesday 10th: Build distribution zips for Weld and TCK, QA run  
> sanity checks, upload to SeamFramework.org
>     - Ondrej, can you schedule some time for this? Either your Tuesday  
> afternoon/evening or your Wednesday morning I guess.

Sure.

> * Wednesday 11th: Submit Final Draft of spec, TCK 1.0.0 and Weld 1.0.0  
> to JCP.
> 
> As you can see the schedule is tight, so please ensure you have all  
> your changes in by the freeze date, or experience my wrath ;-)
> 
> Finally, thanks for all your hard work so far!
> 
> Pete
> 
> [1] Yes, I know this is all upside down, and we should use 1.0.0 of  
> the TCK in Weld 1.0.0 however it gives us a little more time to add  
> tests to the TCK, so is worth the weirdness.