[wildfly-dev] Upcoming WF10 Dates (Reminder)

Emmanuel Bernard emmanuel at hibernate.org
Wed Sep 2 10:37:47 EDT 2015


Hey,

Just a quick heads up on Hibernate Search.

We are planning to get our 5.5 Final in time for Sept 9th and WildFly CR1. But there is a small chance that we split a bit and that we would only get a CR in time for WildFly CR1. We’re working on the easier solution of course :)

Emmanuel



> On 13 Aug 2015, at 19:42, Jason Greene <jason.greene at redhat.com> wrote:
> 
> Hello Everyone,
> 
> First off, I just wanted to say thank you everyone for hitting the major deliverables for the WF10 Beta release that went out over the weekend! 
> 
> The remaining schedule for WF10 is as follows:
> 
> WildFly 10 CR1              - September 9th  
> WildFly 10 CR2 (if needed)  - September 16th 
> WildFly 10 Final            - October 8th (contigent on certification)
> 
> So that means we have 26 days (17 workdays left) to:
> 
> - Stabilize features brought in during Alpha/Beta cycle
> - Finish/polish compatibility (transformers, management ops, etc)
> - Upgrade all components to Final (preferable) or CR (exceptional)
> - Fix broken and/or intermittent tests relating to the above
> - Address any other loose ends
> 
> We should avoid (if possible) introducing new major features to allow for enough time to do the above. Let me know ASAP if thats a problem.
> 
> Thanks!
> 
> --
> Jason T. Greene
> WildFly Lead / JBoss EAP Platform Architect
> JBoss, a division of Red Hat
> 
> 
> _______________________________________________
> wildfly-dev mailing list
> wildfly-dev at lists.jboss.org
> https://lists.jboss.org/mailman/listinfo/wildfly-dev




More information about the wildfly-dev mailing list