[jboss-dev] Re: JBoss-AS-5.0.x-TestSuite-sun15

Ryan Campbell rcampbel at redhat.com
Tue Dec 18 17:09:35 EST 2007


Taking 7 hours doesn't mean it's stuck:

http://hudson.jboss.org/hudson/view/JBoss%20AS/job/JBoss-AS-5.0.x-TestSuite-sun15/buildTimeTrend

Note that build #248 (a valid run) took 7 hours on conf2-linux.


Dimitris Andreadis wrote:
> http://hudson.qa.jboss.com/hudson/view/JBoss%20AS/
> 
> After the library repository came in synch again, I triggered both
> JBoss-AS-5.0.x-TestSuite-sun15 and later
> JBoss-AS-5.0.x-TestSuite-sun15-noip.
> 
> The latter finished first and it shows more or less the usual numbers
> ~200 failures with some transient ones.
> 
> The main JBoss-AS-5.0.x-TestSuite-sun15 has already taken 7 hours, 2
> hours more than the usual so maybe it's stuck and needs to be killed.
> 
> Scott M Stark wrote:
>> Ok, thanks.
>>
>> Shelly McGowan wrote:
>>> Scott,
>>>
>>> There is one currently in progress - almost done.  Internal URL can be
>>> viewed at:
>>>
>>> http://hudson.qa.jboss.com/hudson/view/JBoss20AS/job/JBoss-AS-5.0.x-TestSuite-sun15/250/
>>>
>>>
>>>
>>> Once this is done it will be published to https://hudson.jboss.org
>>>
>>>
>>>
>>> Shelly
>>
> 




More information about the jboss-development mailing list