[jboss-dev] Re: Plan for JBossAS 4.2.0.CR1 - Your Help is Needed
Adrian
adrian_brock at jboss.org
Wed Jan 24 12:16:18 EST 2007
Is somebody looking at getting the JBoss Transactions integration
configured properly like I explained on a previous e-mail?
http://lists.jboss.org/pipermail/jboss-development/2007-January/004776.html
On Wed, 2007-01-24 at 10:15 -0600, Dimitris Andreadis wrote:
> Hi folks,
>
> We are shooting for Feb/26th for JBossAS 4.2.0.CR1, which is only 4.5
> weeks away. As a consequence:
>
> 1) We must finish with all development/bug fixing tasks by Feb/5th.
> Anything not done until then will be deferred.
>
> 2) EJB3 team has an additional week to work (until Feb/12th) and a
> couple more days to finish any integration tasks.
>
> 3) If you are not doing features development, please help *now* fixing
> the testsuites. We are looking a lot better (93%) than last week (~70%)
> but there is still way to go.
>
> http://cruisecontrol.jboss.com/cc/buildresults/jboss-4.2-testsuite-1.5
>
> There a few things broken mainly due to
>
> tomcat->jboss-web transition,
> jrmp->unified invoker changes
> jbossTM->jbossTS(arjuna) switch
>
> Most failing tests are in the following categories:
>
> org.jboss.test.cluster.test
> org.jboss.test.cmp2.audit.test
> org.jboss.test.cmp2.simple
> org.jboss.test.compatibility.test
> org.jboss.test.jacc.test
> org.jboss.test.jca.test
> org.jboss.test.testbeancluster.test
> org.jboss.test.tm.test
> org.jboss.test.txiiop.test
> org.jboss.test.web.test
> org.jboss.test.webservice.*
> ...
>
> 4) We want to pass as much (or all?) of TCK1.4 for 4.2.0.CR1 :) I wanted
> to delay this until we get most of the jboss testsuites passing, but we
> can't delay this any longer.
>
> JBoss 4.2 is a priority, so whether it is working on JIRA tasks,
> testsuites, fixes or TCK stuff, there is plenty of work to do for
> everyone, so your help is very much (and urgently) needed.
>
> If you see issues with this schedule, let me know.
>
> We'll probably create and assign JIRA tasks for the testsuites/TCK fixes
> (we only recently managed to get some good teststuite runs), but please
> don't wait for that and be proactive.
>
> Thanks
> /Dimitris
>
>
>
>
> --
> xxxxxxxxxxxxxxxxxxxxxxxxxxxx
> Dimitris Andreadis
> JBoss AS, Project Lead
> JBoss, a Division of Red Hat
> xxxxxxxxxxxxxxxxxxxxxxxxxxxx
--
xxxxxxxxxxxxxxxxxxxxxxxxxxxx
Adrian Brock
Chief Scientist
JBoss, a division of Red Hat
xxxxxxxxxxxxxxxxxxxxxxxxxxxx