[jboss-dev] AS 5.1 Component Project Schedule

Scott Stark sstark at redhat.com
Thu Feb 5 12:32:58 EST 2009


We need to decide by next Tuesday whether there will be a profile 
service spi update.
https://jira.jboss.org/jira/browse/JBAS-6472

Jason T. Greene wrote:
> Project Leads,
>
> The next planned AS release is 5.1 Beta which we are targeting for a 
> March release, and a following GA in April (provided no major problems).
>
> I need to know what versions of your respective components you would 
> like included in this release. These would preferably be of CR or 
> better quality, although a beta release may be OK if you are confident 
> you can get a GA shortly thereafter. It would also be helpful if you 
> could limit the scope of whatever version you are targeting for AS 
> inclusion to be the features that benefit AS.
>
> Keep in mind that we are transitioning to a frequent release cycle for 
> the AS, so there is no need to rush your project to make this release. 
> The more stable the project releases are, the less time it takes 
> getting the AS ready to release.
>
> Thanks!
>




More information about the jboss-development mailing list