Something to note:
we need to make sure commits to Branch_5_0 are also ported to Branch_5_x and trunk, where it
makes sense.
I've seen a few cases were changes were applied only, e.g. to Branch_5_0 and trunk so
they'll be missing from 5.1/EAP. I don't know if we can create a JIRA filter to catch issues
fixed for 5.0.1.GA AND NOT 5.1.x
Also, the JMS examples, I don't think they belong to the AS source tree, they need to be
moved to the documentation.
Jason T. Greene wrote:
> 5.1 Beta1
> ---------
> Code Freeze: March 9th
> Release: March 16th
>
> The primary/required goal for this release is completion of all Profile
> Service blockers, to facilitate the inclusion of the console:
> https://jira.jboss.org/jira/browse/JBAS-6470
>
> All other planned component updates for this release are located here:
> https://jira.jboss.org/jira/browse/JBAS-6156
>
> If one of these subtasks is assigned to you, and you can not complete
> this in *2 weeks*, please let me know, so I can reschedule it to CR1.
> Also please review the JIRA issues assigned to you and reschedule them
> if you can not complete them for this release.
>
> 5.1 CR1
> -------
> Code Freeze: April 6th (Tentative)
> Release: April 13th (Tentative)
>
> The primary/required goal is inclusion of the embedded console. A
> secondary goal is including JBM 2 as either an optional or main JMS
> provider. These dates could slip a few more weeks depending on the
> console timeline.
>
> All major component upgrades need to be completed and in CR quality for
> this release (with the exception of tech preview features.
>
> 5.1 GA
> ------
> Code Freeze: May 4th (Tentative)
> Release: May 18th (Tentative)
>
> The primary/required goal is of course all tests (including TCK) cleared
> and all assigned bugs resolved.
>
>
> Any questions, feedback?
>
>