[jboss-dev] VFS3 update in MC

Ales Justin ales.justin at gmail.com
Tue Feb 16 05:10:58 EST 2010


> Will everything be set to begin the VFS3 integration in MC at 6PM CET? 

Since no-one complained about it, I would expect we're ready.

> The order of integration is listed at http://community.jboss.org/wiki/VFS3MigrationStatus.
> 
> Should we plan to get through the bulk of the projects right away, or just plan to get through the first couple projects on day one, and see how it goes?  I think we should plan to get the trunks back on line as soon as possible.  

The first 5 should be done in a single shot ("atomic" :-)
the rest can be done later (tomorrow, ...) - in group per project.

CL
* https://jira.jboss.org/jira/browse/JBCL-151
* https://jira.jboss.org/jira/browse/JBCL-152

McAnn
* just create new 1.0.0.Alpha2
--> needs to be generalized anyway

Deployers:
* https://jira.jboss.org/jira/browse/JBDEPLOY-238
* https://jira.jboss.org/jira/browse/JBDEPLOY-239
* https://jira.jboss.org/jira/browse/JBDEPLOY-240

> Let me know when we are ready to go.  

We're ready. ;-)

> > I will send updates with the progress and keep the above document up to date with the status.

OK.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.jboss.org/pipermail/jboss-development/attachments/20100216/cb4c175e/attachment.html 


More information about the jboss-development mailing list