This plan sounds good - but - I thought that the plan for 5.0.1/3.3.1 was to fix these bugs, and no others?
> JBIDE-12249, A lot of failures to install from marketplace.eclipse.org
> JBIDE-12248, JBoss Tools (Indigo) Installation from Eclipse Marketplace
> fails for Eclipse Indigo 3.7.0 and 3.7.1
>
> Are we also up-ing the versions of some 3rd party plugins?
> JBDS-2212, audit version numbers of features/plugins in JBDS 5.0.0 vs.
> 4.1.3
The release seems to have grown quite a bit from this list.
-- Len
----- Original Message -----
> From: "Jiri Peterka" <jpeterka at redhat.com>
> To: "Nick Boldt" <nboldt at redhat.com>
> Cc: "jbds-pm-list" <jbds-pm-list at redhat.com>,
> jbosstools-dev at lists.jboss.org, external-exadel-list at redhat.com
> Sent: Wednesday, July 11, 2012 12:22:36 PM
> Subject: Re: 3.3.1 / 5.0.1 - more JIRAs coming / latest respin almost
> done
> Deal. We'll finish CR1a testing until end of Friday, please respin to
> GA
> on Sunday if no blockers are reported until end of Friday. No CR1b
> build will be done, I'll move rest of unresolved JIRAs to 3.3.2.
> Thanks, Jirka
> On 07/11/2012 06:01 PM, Nick Boldt wrote:
> > Agree on all counts but this was a super-short runway (due to my
> > PTO
> > starting July 18), and not all the issues we wanted done for
> > Friday's
> > code freeze were done in time.
> >
> > So, yeah, non-ideal and we'll try to do better for the .2
> > maintenance
> > next time around (prolly in September, depending on when 6.0.0.M1
> > gets
> > scheduled.
> >
> > I'll hold off providing you a CR1b, and we can just respin as GA on
> > Sunday, unless you want me to wait until Monday night?
> >
> > On 07/11/2012 04:07 AM, Jiri Peterka wrote:
> >> Hi Nick,
> >>
> >> if there is a new respin for these, it's not possible to perform
> >> new
> >> build re-test in time (this week). For small-mid versions like
> >> 5.0.1
> >> expected procedure is:
> >>
> >> 1. All issues in JIRA for 3.3.1 are fixed first or postponed
> >> 2. Then QE Build for is delivered
> >> 3. QE is testing a build (we need 1 week approximately for a
> >> build) - no
> >> more new JIRA fixes during this period!
> >> 4. If non-trivial tests pass, then sign-off & 1:1 respin to GA, if
> >> not
> >> then new JIRAs are created and we are back at step 1
> >> 5. GA is put to CSP and basic verification is done by QE
> >>
> >> Currently we almost break all those rules which is not good for
> >> smooth
> >> testing process. I know there are be PTO & other planning reasons.
> >> Still
> >> we definitely need to avoid similar situations next time. Mainly
> >> step 1
> >> was not fulfilled and not all JIRAs has been fixed or postponed
> >> first
> >> and some fixes are still coming under QA phase. For QE it's really
> >> impossible to use a new build several times in one week and
> >> provide
> >> consistent testing and test results. And another expectation that
> >> is
> >> valid for small-mid updates is that dev phase on branch is done
> >> when QE
> >> build is coming.
> >>
> >> Thanks for understanding, regards,
> >>
> >> Jirka
> >>
> >> On 07/11/2012 04:27 AM, Nick Boldt wrote:
> >>> Just a heads up that a few more issues have been added to the .1
> >>> pile.
> >>>
> >>> == UNRESOLVED ==
> >>>
> >>> JBIDE-12299 : Widen dependency range to support Mylyn 3.8
> >>>
> >>>
> >>> == RESOLVED, NEEDS VERIFICATION ==
> >>>
> >>> JBIDE-12273 : The Source Lookup plugin is not compatible with m2e
> >>> 1.1
> >>> (m2e Juno)
> >>>
> >>> JBIDE-12111 : dynamically set the maven-compiler-plugin for seam
> >>> projects, in order to avoid constraint violation occurring when
> >>> mavenizing seam 2.3 projects
> >>>
> >>> JBIDE-12207 : Bump default Seam version in the JBoss Maven Facet
> >>> wizard page
> >>>
> >>> JBIDE-11310 : resetting models when user switches the openshift
> >>> user
> >>>
> >>> JBDS-2219, JBDS-2220, JBDS-2221 : central connector tweaks for
> >>> mylyn
> >>>
> >>>
> >>> == VERIFIED CLOSED ==
> >>>
> >>> JBDS-2218 : add eclipse-cs to Central
> >>>
> >>> --
> >>>
> >>> Looks like the affected components have all built and now we're
> >>> just
> >>> waiting on the new updatesite/installer build for JBDS to finish.
> >>>
> >>
> >>
> >
--
Len DiMaggio (ldimaggi at redhat.com)
JBoss by Red Hat
314 Littleton Road
Westford, MA 01886 USA
tel: 978.392.3179
cell: 781.472.9912
http://www.redhat.com
http://community.jboss.org/people/ldimaggio
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://lists.jboss.org/pipermail/jbosstools-dev/attachments/20120711/e22c81d1/attachment-0001.html
-------------- next part --------------
A non-text attachment was scrubbed...
Name: RHxJBpngthumb.png
Type: image/png
Size: 9435 bytes
Desc: not available
Url : http://lists.jboss.org/pipermail/jbosstools-dev/attachments/20120711/e22c81d1/attachment-0001.png
More information about the jbosstools-dev
mailing list