Keycloak 1.7 CR1 is scheduled to be released on 2nd December (Wed). I'd
like everything to be done by end of 30th November (Mon). Then we'll do
some testing on Tuesday.
Unless any major issues are reported Keycloak 1.7 Final will be released
the following week.
For releases in the future we'll aim for the following:
* Complete work by end of Monday
* Test on Tuesday
* Release CR1 on Wednesday (Friday at the latest)
* New CR release ASAP as major issues are fixed
* Release Final one week after last CR
Show replies by date