----- Original Message -----
From: "Marek Posolda" <mposolda(a)redhat.com>
To: keycloak-dev(a)lists.jboss.org
Sent: Thursday, 31 July, 2014 8:16:22 PM
Subject: Re: [keycloak-dev] Remaining work for beta-4
On 31.7.2014 15:50, Bill Burke wrote:
> We MUST release by Wednesday. All commits after Friday need to be done
> very carefully. This means that you've run a full build and tested the
> distribution and demos. Aerogear and Stan (among others) need a release...
>
> On 7/31/2014 9:24 AM, Stian Thorgersen wrote:
>> Outstanding work for beta-4:
>>
>> * User federation - what's the status?
> Still working on UI and small issues. Should be done Friday.
>
>> * Turn off cookie cache for all http clients (KEYCLOAK-537) - not sure I
>> understand this issue? isn't sticky sessions something that's
configured
>> by the load balancer?
> Push this to 1.0.Final release. The Apache HTTP Client instance is
> shared by the Adapter. Cookie caching is on by default. IIRC, sticky
> sessions by mod-jk are done via a cookie. Thus accessCodeToToken
> requests will not be load balanced.
>
>> * RealmModel should have a link to realm admin app (KEYCLOAK-486) - I
>> don't think the admin console should refer to the app by name, instead it
>> should either have a link or at least the id of the app associated with
>> the realm
> Can be pushed to 1.0.Final release, IMO.
>
>> * Issue with deploying on AS7 (KEYCLOAK-572) - should be fixed with new PL
>> release, but do we really care about supporting AS7?
>>
> Yes we care about AS7. We need a release from Picketlink on Monday so
> we can test on Tuesday. We will have to make sure that picketlink
> modules are excluded in jboss-deployment-structure.xml and we include
> the picketlink modules directly. Patching picketlink modules directly
> is not an option.
>
>> Issues I propose we push to beta-5:
>>
> I don't think we'll have a beta-5. Next release will be 1.0.Final, ASAP
> after beta-4.
>
>> * LDAP sync - should this go into beta-5? or even wait until after final?
> +1 Marek is close, but should wait until after beta-4 is out.
+1, Pedro is releasing picketlink today, but I am on PTO tomorrow. I can
finish sync on Monday though, but looks that it's too late for the
release...
We need updated PL for beta-4. I'll ping Pedro and try to upgrade it today.
>
>> * Stress tests (KEYCLOAK-514) - we still haven't tested with a large
>> amount of users
I've tested with max 3000 users so far. I think I will need to setup
jenkins job for add big amount of users into DB and then test them.
Marek
>> * DB optimizations (KEYCLOAK-515) - maybe push this to after final?
>> * "Transaction not active" while performing a shutdown (KEYCLOAK-470)
- I
>> can't replicate this, do we close or just set to no fix version?
> close. I coudln't replicate either.
>
>
>
_______________________________________________
keycloak-dev mailing list
keycloak-dev(a)lists.jboss.org
https://lists.jboss.org/mailman/listinfo/keycloak-dev