The new invocation library, which is the basis of for the ejb client etc. is currently
developed in a branch. There are still about 130-140 test failures, but the team feels it
is time to merge to wildfly master at some stage later this week. This will get more
visibility of the failures and also lower the barrier of entry for whoever can jump in and
help fix the failures.
Are there any objections to merging this?
From my point of view we would need to @Ignore the failing tests since
there are enough transient failures in our testsuite to make it hard to find usual
suspects if the number of failed tests is large. We could set up another CI job against a
branch which is master with the @Ignores reverted, and I could keep that up to date as I
merge to master, so that we get a good picture of the current testsuite failures.