Today is my day for posting about schedule stuff.
https://lists.jboss.org/archives/list/wildfly-dev@lists.jboss.org/thread/...
is about big picture; now a more tactical post.
I'd like to do a 29.0.0.Alpha1 on about May 1 or 2. This would be like some
of the alpas we did for 27; minimal effort and fuss, just build and deploy
the server to maven and provide any other deliverables that folks have the
time and inclination to do.
The reason for this is because this month there's likely to be a fair
amount of code re-organizing and deprecated code removal work going on, and
perhaps some feature work in the provisioning area. We're aiming to get the
bulk of that done this month, and I've heard from some folks that having an
alpha in maven that incorporates that work will be helpful.
I figure we'd want PRs that would go into the alpha to be ready for merge
by the 26-27th.
These are not at all precise dates.
Best regards,
Brian