Manik Surtani updated ISPN-1106:
--------------------------------
Status: Resolved (was: Pull Request Sent)
Fix Version/s: 5.0.0.FINAL
(was: 5.0.0.CR4)
Resolution: Done
Rehashing into a running cluster causes shared processing lock
contention
-------------------------------------------------------------------------
Key: ISPN-1106
URL:
https://issues.jboss.org/browse/ISPN-1106
Project: Infinispan
Issue Type: Bug
Affects Versions: 5.0.0.CR2
Reporter: Erik Salter
Assignee: Dan Berindei
Fix For: 5.0.0.FINAL
Attachments: cacheTest.zip, ISPN-1106.log
On our initial test of 5.0.0.CR2, we wanted to test the cluster's rehashing
behavior/performance and if all locks were cleaned up.
The test was to start two nodes, then add a third node, all the while issuing commands to
it.
Upon adding a third node, the cluster becomes inoperable. The stack traces is in the
following location:
http://dl.dropbox.com/u/10929737/5.0.0.CR2/server_node1.log,
http://dl.dropbox.com/u/10929737/5.0.0.CR2/server_node2.log,
http://dl.dropbox.com/u/10929737/5.0.0.CR2/server_node3.log
--
This message is automatically generated by JIRA.
For more information on JIRA, see: