Nick Boldt commented on JBIDE-24789:
------------------------------------
You're asking for the exact process we've used for the last year, which we decided
was unnecessary overhead. You can't got 3 days without committing to master? Each
sprint is 21 days -- this gives you 18 days for commits and 3 days for accumulation of
PRs, writing doc/N&N, and preparing for the forthcoming sprint.
Find a way to avoid freeze of master for several days
-----------------------------------------------------
Key: JBIDE-24789
URL:
https://issues.jboss.org/browse/JBIDE-24789
Project: Tools (JBoss Tools)
Issue Type: Task
Components: build
Affects Versions: 4.5.0.Final
Reporter: Aurélien Pupier
Currently, for each milestone, final release, the master branch is frozen for several
days which is decreasing productivity and increase risk at the end of code freeze (as
everybody wants to merge a lot of PRs at the same time)
it would be nice to find a way to avoid the freeze on the master branch.
Proposal:
- create a branch for each milestone/release:
-- it allows to continue working on master
-- it allows to provide blocker/critical fix if needed on the branch
--