Hi,
We had a call earlier today discussing how to steer the delayed 3.2.1.CR2 (assumed to
become final) and 3.2 M2
The short version is that 3.2.0.M2 stays as planned and we shift/bend 3.2.1.CR2 around
it.
That gives the following schedule:
1st June: 3.2.1.CR1pushed out to staging today (Nick will post about that when it
happens)
14th June: 3.3.0.M2 code freeze
~16th June: 3.3.0.M2 build candidate for QE/smoketesting
19th June: What's'new Ready for review/assembly
22nd June: 3.3.0.M2 release (together with AS7/Eclipse Indigo)
27th June: 3.2.1.CR2 Codefreeze
~30th June: 3.2.1.CR2 build candidate for QE/full testing on staging
~15th July: 3.2.1.Final rebuild / release
I'll get jira updated tonight/tomorrow to reflect these dates.
/max