Hi Jeff,
thanks for explanation.
Josef
On Tue, Jul 30, 2019 at 1:28 PM Jean-Francois Maury <jmaury(a)redhat.com>
wrote:
Joseph,
the idea is to get the TP ready ASAP (so that we can fix broken builds)
and you notice that the bits included into this TP are ready from September
18
so that the TP will not be build in one day
On Tue, Jul 30, 2019 at 8:42 AM Josef Kopriva <jkopriva(a)redhat.com> wrote:
> Hi Jeff,
>
> I would just add sign-off dates for QE:
> 24-Sep-2019 - 4.13.0.AM1 QE sign-off
> 8-Oct-2019 - 4.13.0.Final QE sign-off
>
> And I have a question regarding Final TP freeze: is it enough one day for
> TP update? AM1 release is scheduled for 24-Sep-2019 and the next day is
> Final TP freeze. Usually Final TP freeze is one day before Final freeze -
> in this release it would be 2-Oct-2019.
>
> Thanks.
> Josef
>
> On Mon, Jul 29, 2019 at 11:08 PM Jean-Francois Maury <jmaury(a)redhat.com>
> wrote:
>
>> Hello,
>>
>> please find the proposed schedule dates for JBoss Tools and CodeReady
>> Studio based on Eclipse 2019-09
>>
>> *Upstream:*
>> 2019-09.M1 19-Jul-2019
>> 2019-09.M2 9-Aug-2019
>> 2019-06.M3 30-Aug-2019
>> 2019-09.RC1 6-Sep-2019
>> 2019-09.RC2 13-Sep-2019
>> 2019-09 GA 18-Sep-2019
>>
>> *Sprints:*
>> 12-Jun-2019 2-Jul-2019 168 Nymphea
>> 3-Jul-2019 23-Jul-2019 169
>> 24-Jul-2019 13-Aug-2019 170
>> 14-Aug-2019 3-Sep-2019 171
>> 4-Sep-2019 24-Sep-2019 172 Orchid
>> 25-Sep-2019 15-Oct-2019 173
>>
>> *Dependencies*
>> EAP CD 17 GA 25-Jul-2019
>> EAP 7.3 Beta 26-Aug-2019
>> Wildfly 18 Beta 4-Sep-2019
>> Wildfly 18 19-Sep-2019
>> EAP CD 18 GA 12-Nov-2019
>> EAP 7.3 GA 21-Jan-2020
>>
>> So, in chronological order:
>> devex #168 2-Jul-2019
>> 2019-09.M1 19-Jul-2019
>> devex #169 23-Jul-2019
>> EAP CD 17 GA 25-Jul-2019
>> 2019-09.M2 9-Aug-2019
>> devex #170 13-Aug-2019
>> EAP 7.3 Beta 26-Aug-2019
>> 2019-06.M3 30-Aug-2019
>> devex #171 3-Sep-2019
>> Wildfly 18 Beta 4-Sep-2019
>> 2019-09.RC1 6-Sep-2019
>> 2019-09.RC2 13-Sep-2019
>> 2019-09 GA 18-Sep-2019
>> Wildfly 18 19-Sep-2019
>> devex #172 24-Sep-2019
>> devex #173 15-Oct-2019
>>
>> So, the proposed schedule could be the following:
>>
>> 17-Sep-2019
>> 4.13.0.AM1 TP Code Freeze (based on 2019-09.RC1)
>> 18-Sep-2019
>> 4.13.0.AM1 Code Freeze
>> 20-Sep-2019
>> 4.13.0.AM1 staged for QE
>> 24-Sep-2019
>> 4.13.0.AM1 released
>> 25-Sep-2019
>> 4.13.0.Final TP Code Freeze (based on 2019-09 GA)
>> 2-Oct-2019
>> 4.13.0.Final Code Freeze
>> 4-Oct-2019
>> 4.13.0.Final staged for QE
>> 11-Oct-2019
>> 12.13.0.GA pushed to stage by RCM
>> 14-Oct-2019
>> 12.13.0.GA pushed to prod by RCM
>> 15-Oct-2019
>> 12.13.0.GA announced
>>
>> So, the bits will be based on 2019-09 and will support Wildfly 18 and
>> EAP 7.3 Beta (Tech Preview)
>> WDYT ?
>> --
>>
>> Jeff Maury
>>
>> Manager, DevTools
>>
>> Red Hat EMEA <
https://www.redhat.com>
>>
>> jmaury(a)redhat.com
>> @RedHat <
https://twitter.com/redhat> Red Hat
>> <
https://www.linkedin.com/company/red-hat> Red Hat
>> <
https://www.facebook.com/RedHatInc>
>> <
https://www.redhat.com>
>> <
https://redhat.com/summit>
>>
>
>
> --
>
> Josef Kopriva
>
> Quality Engineer
>
> Red Hat <
https://www.redhat.com/>
>
> Purkynova 111
>
> 612 00 Brno IM: jkopriva
> <
https://www.redhat.com/>
>
--
Jeff Maury
Manager, DevTools
Red Hat EMEA <
https://www.redhat.com>
jmaury(a)redhat.com
@RedHat <
https://twitter.com/redhat> Red Hat
<
https://www.linkedin.com/company/red-hat> Red Hat
<
https://www.facebook.com/RedHatInc>
<
https://www.redhat.com>
<
https://redhat.com/summit>