We are using JBPM 3.2.6.SP1 in production. I have read here that process definitions are
about 80% convertible going to JBPM 4. However, I have not found any information on
migrating the underlying database.
Loosing all existing process data is not really a good incentive to convince our users to
allow me to upgrade to 4.X.
It would be really nice to get the new EJB command interface which is far more functional
than the 3.X branch has. I have wrappers around all calls to JBPM so that aspect of the
upgrade may be the easiest. Reworking process definitions seems straight forward and we
have only four distinct processes currently.
The greatest dilemma at this point is pending processes in the system.
Any ideas how the upgrade could be made without loosing all existing data?