Hi,
A couple of questions:
1) Say I have a review process for a business item (awaiting review, reviewed, etc).
Sometimes (say 2% of the time) the item needs to be reviewed again. I'm using the
business key of the item as the business key of the process (so I can find it). If I
start a new jBPM process with the same key I get problems later on due to Jbpm saying more
than one process for a key. Should I reuse the same process and signal it some how to
start again? Or should I some how use a different key?
2) Is there any delete functionality to clear up all ended processes? Can you point me in
the direction of it.
Thanks
Tom