By wrongly represented, I mean that I must be at one time in two nodes :
- the one which waits until X days
- the one which waits the manual validation
So I guess I must have something like a fork in my workflow, so that it is possible for me
to be in two nodes at the same time.
But if I add the fork, I have to wait until both tasks are completed, and I don't want
that.
I don't know if I'm clear enough.
And to answer to your questions :
- The query is sent at the start state
- I enter the node 'attente_accord_tacite' when the time declared in the query is
reached
Thanks