zecas zecas [
http://community.jboss.org/people/zecas] created the discussion
"Releasing Task to a Group (Swimlane defined)"
To view the discussion, visit:
http://community.jboss.org/message/540802#540802
--------------------------------------------------------------
Hi,
I have the following process definition:
<?xml version="1.0" encoding="UTF-8"?>
<process name="Request Project"
xmlns="http://jbpm.org/4.3/jpdl">
<swimlane name="user-list" candidate-groups="user"
candidate-users="mary,alex" />
<start name="start">
<transition to="request_project" />
</start>
<task name="request_project" swimlane="user-list">
<transition to="end" />
</task>
<end name="end" />
</process>
After starting an instance, I can assign the task to a specific user:
TaskService taskService = processEngine.getTaskService();
taskService.takeTask("310002", "peter");
Now I can pickup the task with user "peter" and complete it.
But I don't want to do it, I want to release the task back to the group.
How can I do it? I can't seem to find a way of doing it.
Thanks
--------------------------------------------------------------
Reply to this message by going to Community
[
http://community.jboss.org/message/540802#540802]
Start a new discussion in jBPM at Community
[
http://community.jboss.org/choose-container!input.jspa?contentType=1&...]