Hi All,
Looking at the jBPM5 examples/documents/threads on general timing, I've come to
the following conclusions....
1. tasks in jBPM5 do not support due dates.
2. the business.calendar.properties file is not supported in jBPM5
3. The only timing features support appears to be wait for xxx msec before a executing
task.
If these are correct, I'm trying to work out how you might model a business
process where a task needs to be escalated within (say) 2 business days. Does anyone have
an approach for this in JBPM5 ?
--------------------------------------------------------------
Reply to this message by going to Community
[
http://community.jboss.org/message/600198#600198]
Start a new discussion in jBPM at Community
[
http://community.jboss.org/choose-container!input.jspa?contentType=1&...]