If possible, I'd prefer to have everything done by Thursday so that
build respin problems (like the one that caused *over 60 build failure
emails* to be produced yesterday) can be mitigated.
If you have any reason why you won't be ready for code freeze for 4.0.1
by EOD Thurs Feb 28, let me know ASAP.
Subject to change, the planned schedule for 4.0.1 is as follows:
2013/03/01 4.0.1.CR1 Code Freeze
2013/03/04 4.0.1.CR1 QE Start
2013/03/14 4.0.1.CR1 QE End
2013/03/15 4.0.1.CR1 Dev Milestone available
2013/03/18 4.0.1.CRX Quiet Period
2013/03/22 4.0.1.Final Released on
jboss.org
N
On 02/27/2013 01:47 PM, Max Rydahl Andersen wrote:
Hi,
We are trying to get a build running from jbt 4.0.x branch on friday to send to QE as an
upcoming JBT 4.0.1.
The branches are already made for JBT 4.0.x so its just a matter of making sure your
pom/plugin's are properly version bumped.
If you got things that need fixed please get the PR's in for review ASAP.
/max
_______________________________________________
jbosstools-dev mailing list
jbosstools-dev(a)lists.jboss.org
https://lists.jboss.org/mailman/listinfo/jbosstools-dev
--
Nick Boldt :: JBoss by Red Hat
Productization Lead :: JBoss Tools & Dev Studio
http://nick.divbyzero.com