All,
As previously discussed, we are aiming for a 10-12w release cycle of patch releases for
Weld and for the CDI TCK. This means the 1.0.1 releases should happen around the 4th Feb.
To this end, the release schedules are:
CDI TCK
1.0.1.CR1: 21st January (Thursday this week)
1.0.1: 4th Feb
Weld
1.0.1.CR1: 28th January (Thursday next week)
1.0.1: 4th Feb
If you are working on issues for 1.0.1 please review the issues you are assigned, and
check that you think you can make the CR1 dates above. If you can't, please ping me
and we can either slip the issue to 1.0.1 or find some help for you.
Current assignments by the numbers are:
* Aslak - 1 issue (WELD-362)
* Dan - 2 issues (WELD-27, WELD-287)
* David - 3 issues (WELD-4, WELD-337, WELD-365)
* Marius - 10 issues (WELD-291, WELD-269, WELD-312, WELD-325, WELD-36, WELD-314, WELD-377,
WELD-356, WELD-272, WELD-274)
* Nik - 4 issues (WELD-32, WELD-271, WELD-361, WELD-348)
* Roger - 5 issues (WELD-273, WELD-30, WELD-206, WELD-31, WELD-303)
* Shane - 1 issue (WELD-257)
* Stuart - 2 issue (WELD-335, WELD-309)
leaving
* Pete/Unassigned - 27 issues
Thanks!
Pete