Guys, thanks for all the hard work!
On Thu, Feb 26, 2009 at 3:41 PM, Pete Muir <pmuir(a)redhat.com> wrote:
All,
I would like to release beta1 on 3rd March. Outstanding for this we have:
* Dependent object destruction: Nik, what is the status of this?
* Conversations: Nik, what is the status of this?
* Hierarchical managers: I will work on this next week
* Disposal methods: Daniel Roth is working on a patch for this
* Injection into EJBs: I will work on this next week
* Injection into servlets: I will work on this next week
* TX observers: implemented, but has issues. David, if you can get this done
for the release that would be ace!
* Async observers: needs implementing. Again, David, if you can get this
done, that would be great...
* A number of small issues thrown up by the TCK. I will work on this
tomorrow
Please let me know if you are going to have issues finishing a particular
features (including TCK tests) for the 3rd and we can either slip the
feature or slip the release date.
Thanks!
--
Pete Muir
http://www.seamframework.org
http://in.relation.to/Bloggers/Pete