"danj" wrote : "schrouf" wrote : Up to my knowledge it has always been
"time from finish until next start".
|
| Strange. We have a nightly job that takes somewhere between 8 s and 50 min. We have
configured it with SchedulePeriod = 24 * 60 * 60 * 1000.
|
| Using 3.2.5, the job has started same time every night (01:00), and finishin within
the hour, in good time before people arrive in the morning.
|
| However, since upgrading to 3.2.7, the jobs have start "slipping", i e
starting later and later. And, the slip is exactly the time the job took, i e starting at
the last nights finish-time. If this is the intended behaviour, it feels strange.
I have exactly same problem, so after more then a year I want to ask, if there was any
developement of this issue.
Thanks Petr
View the original post :
http://www.jboss.com/index.html?module=bb&op=viewtopic&p=3969128#...
Reply to the post :
http://www.jboss.com/index.html?module=bb&op=posting&mode=reply&a...