I'm missing the upgrade to JGroups 3.2.5 in the list :-(
I also suggest moving the release data to Dec 22: then you don't have to
do the release as the 21st is the end of the world ha ha :-)
On 12/18/12 7:31 PM, Mircea Markus wrote:
Hi,
Next Infinispan release(5.2.0.CR1) is scheduled for Friday 21 Dec.
We still have 19 issues (blocker + critical) that must make it in for
CR[1]. Besides this we are still waiting for input from QA - hopefully
things will stabilise at this stage.
Realistically speaking we won't be able to solve all 19 issues this
the end week of this week, so I've moved the release date to Jan 4th
(Friday).
Also please review the JIRAs[1] assigned to you and approach the
blocker/critical JIRAs first.
[1]
http://goo.gl/iV9MQ
Cheers,
--
Mircea Markus
Infinispan lead (
www.infinispan.org <
http://www.infinispan.org>)
_______________________________________________
infinispan-dev mailing list
infinispan-dev(a)lists.jboss.org
https://lists.jboss.org/mailman/listinfo/infinispan-dev
--
Bela Ban, JGroups lead (
http://www.jgroups.org)