Jan Uhlir [
https://community.jboss.org/people/espinosa_cz] created the discussion
"Re: How to create a simple waiting workflow"
To view the discussion, visit:
https://community.jboss.org/message/716971#716971
--------------------------------------------------------------
Mauricio Salatino wrote:
..You need to add a <task> -> service task node and then write an implementation
of the WorkItemHandler class and do not complete the workitem inside the implementation.
That will cause your process to wait until you finally decide to complete it...
Good
tip. Thank you.
Now I am stuck on how to signalize the custom task (MyWaitTask1WorkItemHandler aka
MyWaitTask1) to complete and continue to the next task.
According to this
https://community.jboss.org/message/629016#629016 forum post, it is not
possible to signalize Tasks, only Events:
+In general you cannot just signal any node directly ... however normally you have to
model this as a signal event. (by+ Tihomir Surdilovic+)
+
Please, how should I here apply signal event?
Put an Event element after the MyWaitTask1? Or before? Neither give sense.
At the start of a new process "line"? I saw it in some examples. I puzzles me.
See my post below.
+
+
--------------------------------------------------------------
Reply to this message by going to Community
[
https://community.jboss.org/message/716971#716971]
Start a new discussion in jBPM at Community
[
https://community.jboss.org/choose-container!input.jspa?contentType=1&...]