Maciej Swiderski [
https://community.jboss.org/people/swiderski.maciej] created the
discussion
"Re: Difficult workflow question"
To view the discussion, visit:
https://community.jboss.org/message/732306#732306
--------------------------------------------------------------
Josh, in case we discussed sub process (or task) should not be terminated by end event but
should be canceled (interrupted) by boundary event attached to it. As you can see, there
are multiple instances of the sub process and if one of them completes with expected
result it should throw a signal informing other sub process instances to interrupt their
processing but this particular instance will be completed after event is thrown so no need
to terminate itself. Does that make sense?
--------------------------------------------------------------
Reply to this message by going to Community
[
https://community.jboss.org/message/732306#732306]
Start a new discussion in jBPM at Community
[
https://community.jboss.org/choose-container!input.jspa?contentType=1&...]