We're in CR stages though so what's the point of releasing a CR which actually is
not really a CR? ;)
I can see the point of faster, more frequent releases in BETA/ALPHA stages because we can
push over things, but doesn't make sense doing that in CR.
We did 8 CR releases for 5.0 which was a bit ridicolous ;)
On Jan 4, 2012, at 1:24 PM, Manik Surtani wrote:
+1 on faster and more frequent releases.
On 4 Jan 2012, at 09:17, Tristan Tarrant wrote:
> Dear all,
>
> as you all know 5.1.0.CR2 failed inclusion in AS7 7.1.0.CR1 because of
> ISPN-1644 [1]. Brian Stansberry is asking to reopen the pull request I
> initially opened [2] with an appropriate release. Since we now have
> regular CI builds of both AS7 and Infinispan master snapshots (thanks to
> our great QE team) we can now be a bit more prompt in fixing these
> problems before it's too late. To remain in a spirit of promptness, I
> would recommend getting a CR3 (and possibly further CRs) out as quickly
> as possible to expedite integration and testing. I know a release
> requires a bit of effort (especially on Galder's part, and I'm willing
> to help here if necessary), but I believe both code-bases would benefit
> greatly.
>
> What do you all think ?
>
> Tristan
>
>
>
> [1]
https://issues.jboss.org/browse/ISPN-1644
> [2]
https://github.com/jbossas/jboss-as/pull/981#issuecomment-3344718
> _______________________________________________
> infinispan-dev mailing list
> infinispan-dev(a)lists.jboss.org
>
https://lists.jboss.org/mailman/listinfo/infinispan-dev
--
Manik Surtani
manik(a)jboss.org
twitter.com/maniksurtani
Lead, Infinispan
http://www.infinispan.org
_______________________________________________
infinispan-dev mailing list
infinispan-dev(a)lists.jboss.org
https://lists.jboss.org/mailman/listinfo/infinispan-dev
--
Galder Zamarreño
Sr. Software Engineer
Infinispan, JBoss Cache