"lbrasseur" wrote : I want to change the execution path from one task node to
another. However, there is no transition between nodes (it's a strange requirement for
the application: to be able to make arbitrary state jumps).
|
No, but not very common
"lbrasseur" wrote :
| I tried getting the Token and changing the node to which it points. However, this
causes a lot of exceptions with task instances found on the old node.
|
| There is an easier way to do this?
|
|
In normal nodes you can move the token without a problem. Task nodes are more complex, but
you can try the following
- try configuring the tasks as not signalling (they will not move the token then if they
are ended
- cancel the tasks before moving the token
View the original post :