On 08/03/2012 01:31 PM, Mircea Markus wrote:
> Hi,
>
> The main goal of the next Alpha release is getting NBST(ISPN-1424) out
(alpha-stable). After discussing with Dan and Adrian, here's the action plan:
> - Dan/Adrian will issue a pull request Mon/Tue (6-7 Aug)
> - given the complexity of the change, the review for this is expected to take up to a
week. During this time, besides answering review comments, they will consolidate the
implementation
> - finally the release is estimated to happen at the beginning of the week starting 13
August - the day to be confirmed later on next week
>
> Thanks,
> Mircea
> _______________________________________________
> infinispan-dev mailing list
> infinispan-dev(a)lists.jboss.org
>
https://lists.jboss.org/mailman/listinfo/infinispan-dev
Mircea, I've got ISPN-1978 (allow modules to extend the configuration
schema) nearly ready to go, but I need some extra testing. I'll try and
get it done by the Mon/Tue as well.