Sunil kondkar commented on HAWKULARQE-72:
-----------------------------------------
All work related to test cases is done.
Worked on linking requirements to test cases marking them as 'verifies' the test
case rather than 'relates' is done. ( This is causing missing data in most of the
projects)
Created a doc mentioning some guidelines.
http://pad.engineering.redhat.com/PolarionGuidelines
The following report does not show any missing data.
https://polarion.engineering.redhat.com/polarion/#/project/pylarion/wiki/...
While going through EAP project reports, observed that there are release plans created in
Polarion and requirements are marked as 'planned in' which is not in our case. (
These plans are different from test plans)
Created few release plans like:
Parent: MM-CFME58
Child plans: MM-CFME58-DR1, MM-CFME58-DR2 and MM-CFME58-DR3
link:
https://polarion.engineering.redhat.com/polarion/#/project/JBossON4/plans
Now the remaining task is: Research and link requirements/test cases to the respective
plans in Polarion so as to enble reports viewing according to Polarion plans.
Polarion data cleanup
---------------------
Key: HAWKULARQE-72
URL:
https://issues.jboss.org/browse/HAWKULARQE-72
Project: Hawkular QE
Issue Type: Task
Reporter: Sunil kondkar
Assignee: Sunil kondkar
Task to able to have polarion reports in place.
Reports:
1) PQI Metrics:
https://polarion.engineering.redhat.com/polarion/#/project/JBossON4/wiki/...
2) Standard Reports:
https://polarion.engineering.redhat.com/polarion/#/project/JBossON4/wiki/...
3) Test Run Status by Plan
4) Test Run Status by Plan and chosen fields
Tasks:
1) Find and remove duplicates
2) Each test case has correct fields
* Description
* Level
* Test type and sub type
* Automated or Manual
* Importance (Severity)
3) Do we need to create a plan in below link? (Like EAP team has release plans created
that are used in reports ' Test Run Status by Plan' and 'Test Run Status by
Plan and chosen fields' )
Link:
https://polarion.engineering.redhat.com/polarion/#/project/JBossON4/plans
4) Check if manual test cases are with approved status( Approve if needed)
5) All automated tests (CF-UI test and CFME tests) - need to be changed to Approved from
'Draft' status.
(Need to check if we can have the polarion export job marking it Approved while executed
going forward?)
--