Michael Foley created SWSQE-163:
-----------------------------------
Summary: Create sub-tasks ... and move a few discrete sub-tasks from this
story to sprint #4
Key: SWSQE-163
URL:
https://issues.jboss.org/browse/SWSQE-163
Project: Kiali QE
Issue Type: Sub-task
Reporter: Michael Foley
Assignee: Guilherme Baufaker RĂªgo
The modularization of the CI/CD pipeline is a large topic ... epic or user story. The
first step is to do task breakdown into more discrete units of work.
[~mmahoney] has a slide or google doc outlining, at a high-level, some thoughts. Using
this document as input, I would like to ask [~gbaufake] to work with [~hhovsepy] to
create a set of sub-tasks that represent the planned modularization work in some detail.
Each unit of work should be around 1 or 2 days of work, at most. And taken together,
these sub-tasks will represent the improvements.
Once the sub-tasks are created:
* move this epic out of sprint 4
* move in the specific tasks that are needed for sprint #4
--