Hi Vikram,
Could you provide the source code so that we can reproduce the problem?
Best regards,
Michal
2009/7/13 Vikram Pancholi <vikram.pancholi(a)gmail.com>
Hi,
I am using version 5.1.0 Snapshot for compiler , api and core. My
requirement is as follows
1) Process A -- Main process --loops continuousy though a series of actions
/ splits and joins ...
there is a split constraint written which uses the level (mentioned
below).
2) Process B -- Sub process is as follows
1)Start
2)within process b, i m creating a timer task and sceduling it at say 1000
to insert a fact named Etrigger.
3)Event wait ;;-- waits for Etrigger
4)Increase the value of variable ..say level from 0 -> 1.
5)End the subprocess
But as soon as i insert the fact Etrigger looping of process A hungs up.
I tried using other options as well namely using fusion to insert the
Etrigger, but it doesnt expire even after giving expiry of 1 ms . And i
cannot confgure timer delay using a variable.
Thanks and Regards