https://issues.jboss.org/browse/AS7-4535?page=com.atlassian.jira.plugin.s...
]
Dominik Pospisil commented on AS7-4535:
---------------------------------------
The problem is that there is no easy way how to identify that the CLI has finished writing
stuff to output stream.
Could be done by trying to parse the result line-by-line and guess when the output is
done. However this might not work for all use cases. The other way would be to use CLI API
which is now available (and was not ~5 months ago).
Test framework for CLI-based tests can be very slow
---------------------------------------------------
Key: AS7-4535
URL:
https://issues.jboss.org/browse/AS7-4535
Project: Application Server 7
Issue Type: Bug
Components: Test Suite
Affects Versions: 7.1.2.Final-redhat1
Reporter: David Bosschaert
Assignee: Ondrej Zizka
Priority: Minor
The org.jboss.as.test.integration.management.base.AbstractCliTestBase provides a suitable
API for testing CLI-based operations. However, running tests with a relatively large
number of CLI operations can take a *long* time, seemingly much longer than necessary.
This is probably related to the fact that CLIWrapper.readAllAsOpResult() method always
seems to wait until the lineTimeout has expired.
Typically the WAIT_LINETIMEOUT value is used for this argument. Shortening the timeout is
not an option as I have seen cases where a test would fail when run on a slow machine, but
this only happens occasionally.
It would be *much* better if a timeout was not needed for this and the test would wait
until a certain operation was finished.
This can be observed in org.jboss.as.test.integration.management.cli.JmsTestCase and I
also experienced it when writing the
org.jboss.as.test.integration.osgi.management.OSGiManagementTestCase.
--
This message is automatically generated by JIRA.
If you think it was sent incorrectly, please contact your JIRA administrators:
https://issues.jboss.org/secure/ContactAdministrators!default.jspa
For more information on JIRA, see:
http://www.atlassian.com/software/jira