Hi
I'm going to explain a little better. I have a process that has a form associated with
the start of the process. He has an automatic task (java), which loads some variables.
Then I have implemented a manual task that belongs to Peter and has no associated
graphical interface (I hope explain well). What I want is to complete this task???, Ie
PETER personal tasks, the task is loaded as follows:
Priority Process Task Name Due Date
0 Test-1 buy 2009-11-24 07:20:34
I just want to say that this task is already complete, so that the instance of the process
to finish
I'm new to jBPM and it's been very difficult to handle the jbpm-console console
Thanks
View the original post :
http://www.jboss.org/index.html?module=bb&op=viewtopic&p=4267281#...
Reply to the post :
http://www.jboss.org/index.html?module=bb&op=posting&mode=reply&a...