Can you provide that simple test case, so I don't need to create a new maven
project a flow and a test (Junit with asserts) that show that it's failing?
I understand your situation but try understand mine.
On Wed, Apr 14, 2010 at 2:52 PM, nanic23 <nanic23(a)hotmail.com> wrote:
Hi Mauricio,
My test cases are business components that I can't share. But.... this is
just a very simple situation, nothing complicated here. You can do a very
simple flow that will suspend in a workItem to which you pass a Long (or
Integer) and then after it has been persisted try to reload it to complete
the work item...
In my case, I'm suspending in a HumanTask that just has a regular
WorkItemHandler behind (no Mina server), I am mapping a parameter of type
Long..... I have also tried the Integer option provided in the graphical
eclipse editor and none of them worked. When the flow is resuming and those
variables are getting restored I get the exception indicated on the first
post.
I wanted to point out that it is working fine when the parameter mapped is
a
String instead of a Long or Integer.
I hope this helps clarifying things.
Let me know if you have any other question.
Thanks,
Nick.
--
View this message in context:
http://n3.nabble.com/Resuming-Flow-NPE-when-completing-a-work-item-tp7168...
Sent from the Drools - User mailing list archive at
Nabble.com.
_______________________________________________
rules-users mailing list
rules-users(a)lists.jboss.org
https://lists.jboss.org/mailman/listinfo/rules-users
--
-
http://salaboy.wordpress.com
-
http://www.jbug.com.ar
- Salatino "Salaboy" Mauricio -