Update:
We will be moving the end date of the development work and, therefore, the end date of the
release back by one week. The main reason for this decision is to include the work which
is currently taking place on the FP branch and verify the integration with AS 4.2.2.
The new dates are:
17th March - 2nd May (7 weeks)
Development work continues through this period. We will only consider additional JIRA
tasks if they are definitely bug fixes, new functionality will be assigned to the next
release
5th May - 16th May (2 weeks)
This period covers the final testing of the project, in readiness for the release.
Apologies for this.
Kev