Andrew Dinn commented on JBTM-503:
----------------------------------
Hi Mauro,
RecoveryManager.startRecoveryManagerThread() is called from TransactionManager.start().
There are actually two versions of this class located in the jbossatx.jta and jbossatx.jts
packages. They provide the interface to the Application Server.
I had not noticed that the ExpiredEntryMonitor startup call is made in the constructor.
This is probably not the correct place for it to happen but I htink there is a reason for
it.
I'll note that the periodic recovery instance also gets created in the constructor
(and, if parameter threaded is true, started) whereas it probably ought at most to be
created there and then started and stopped by the recovery manager start and stop calls.
In the periodic recovery case this is done because in some circumstances the instance
needs to be created without being started. Recovery runs as a background thread in the App
Server but it can also be run via direct calls to scan(0 if the recovery manager is
started in a separate recovery process outside the AS. So, this code is dual purpose.
What I have not yet ascertained is why the ExpiredEnrtyMonitor thread is not subject to
the same condition. I think it probably needs to run in either case and since start does
not get called when the recovery manager is in its own process this is a cheap hack to
make sure it always runs.
Anyway, as far as shutting down is concerned I can make one very clear statement. It is
almost never appropriate to use a finalizer to clean up state. The only excuse for using
finalizers is when a library hands out a reference to an instance to client code and
cannot reasonably expect the client code to call a cleanup method to release resources
held by the instance (n.b.in my book any respectable client program ought to guarantee to
release any resources it allocates so this means a finalizer is never justified but
sometimes you cannot pick and choose your clients). The reason it is such a bad thing to
do is that finalizers make GC run like a pig. So it is best to avoid them at all costs.
Ok, that said, I believe it is currently valid to assume that when a recovery manager is
stopped it will not be restarted. Anyway calling start after stop wlll not work because
the start method will try to restart the periodic recovery instance and calling start on a
previously started thread is not valid. Anyway, given this assumption it makes no
difference whether the ExpiredEnrtryMonitor is started in the constructor or in method
start. So, the place to shut down the ExpiredEntryMonitor thread is in
RecoveryManagerImple.stop.
Shutdown the ExpiredEntryMonitor when stopping the RecoveryManager
------------------------------------------------------------------
Key: JBTM-503
URL:
https://jira.jboss.org/jira/browse/JBTM-503
Project: JBoss Transaction Manager
Issue Type: Feature Request
Security Level: Public(Everyone can see)
Components: Recovery
Affects Versions: 4.5
Environment: Tomcat + Spring + DBCP + JBossJTA
Reporter: Mauro Molinari
Assignee: Andrew Dinn
When the recovery manager is started, the implementation RecoveryManagerImple starts the
ExpiredEntryMonitor.
When you stop the recovery manager, however, the ExpiredEntryMonitor is not shut down.
On line 250 of com.arjuna.ats.internal.arjuna.recovery.RecoveryManagerImple there's
the line ExpiredEntryMonitor.shutdown() commented out, with a "TODO why?"
comment immediately before.
I don't know exactly what should be the lifecylce of ExpiredEntryMonitor versus that
of RecoveryManagerImple, however I think that one of the following should happen:
- ExpiredEntryMonitor is started when RecoveryManagerImple is started (rather than
constructed), so that it is shut down when the RecoveryManagerImple is stopped
OTHERWISE
- RecoveryManagerImple provides a way to "dispose" or "disable" it
and this includes the shutdown of ExpiredEntryMonitor
OTHERWISE
- it is documented that stopping the recovery manager needs the ExpiredEntryMonitor to be
stopped too: however, please consider that
com.arjuna.ats.internal.arjuna.recovery.ExpiredEntryMonitor.shutdown() throws a
NullPointerException if called while the ExpiredEntryMonitor has not been started before
and there is no public method to test if it has been started or not; so if I need to write
some code that stops the ExpiredEntryMonitor (without knowing if it has been started or
not) I have to write some ugly code like:
{code:java}
try
{
ExpiredEntryMonitor.shutdown();
}
catch(final NullPointerException e)
{
// ExpiredEntryMonitor had not been started
}
{code}
--
This message is automatically generated by JIRA.
-
If you think it was sent incorrectly contact one of the administrators:
https://jira.jboss.org/jira/secure/Administrators.jspa
-
For more information on JIRA, see:
http://www.atlassian.com/software/jira