We are now entering a timeboxed release process. Starting from next week we will be
adhering to the following schedule
3rd March - 14th March (2 weeks)
JIRA issues will be assigned to the 4.3 release of the project. At this stage we will
consider requests for new functionality.
17th March - 25th April (6 weeks)
Development work continues through this period. We will only consider additional JIRA
tasks if they are definitely bug fixes, new functionality will be assigned to the next
release
28th April - 9 May (2 weeks)
This period covers the final testing of the project, in readiness for the release.
If there is anything you wish to see in the next version of the project then please let us
know *before* March 14th.
Thanks,
Kev
View the original post :
http://www.jboss.com/index.html?module=bb&op=viewtopic&p=4131902#...
Reply to the post :
http://www.jboss.com/index.html?module=bb&op=posting&mode=reply&a...