Folks,
currently we have commited ourselves to a release cycle of eight weeks per minor release
in jbossws . I'd like to improving the predictability of jbossws releases, therefore I
suggest we follow the following rules:
| ---------------------------------
| W1
| W2 Define set of JIRA issues
| ----------------------------------
| W3
| W4
| W5
| W6 Work on issues
| ----------------------------------
| W7
| W8 QA, Docs, Packaging
| ----------------------------------
|
In other words, at the end of W2 there are no more JIRA issues added to a release. At the
end of W6 there are no more code changes.
Upcoming Relases
---------------------
jbossws-1.0.3 => 31-Aug-2206
jbossws-1.0.4 => 31-Oct-2006
Heiko, will handle the following two releases. After that I think it be good if we rotate
the responsibility.
Cheers