"ALRubinger" wrote :
| So now AS requires Dependency Version 2, which breaks EJB3. CR1 is held up because a
switch was flipped right before the milestone, and EJB3 needs to resolve the errors before
CR1 can ship.
|
That coordination should have happened before the shared pom was updated. Each project
should have a subtask on the jira issue for updating the parent pom to version 2, and only
when those are closed the parent is updated.
View the original post :
http://www.jboss.com/index.html?module=bb&op=viewtopic&p=4136469#...
Reply to the post :
http://www.jboss.com/index.html?module=bb&op=posting&mode=reply&a...