Sebastian,
You're thinking is correct: it's a matter of resourcing. The thing is, our job
isn't 100% development ... often there are consultancies, conferences and huge
internal discussions to be done. And I'm only touching the tip of the iceberg here,
unfortunately.
We expect +- 1 week work to get the history in a 'finished' state. Since the code
freeze for 4.3 is extremely close, this time isn't available anywhere (without
actually doing something else). We do hope to get the history done quickly, hopefully
somewhere around christmas (but by then the 4.3 brach will already be made - which means
changes can't be ported from trunk).
Hope this gives you some insight in our 'process'