I'll ask the obvious questions as Jason is and out of contact and this
is time critical.
Have you done a full testsuite run with this change?
How critical is this? Seems awful late for a change to a core library.
On 7/21/10 9:51 AM, Kabir Khan wrote:
Is it too late to upgrade jboss-reflect with this little change?
https://jira.jboss.org/browse/JBREFLECT-135
On 19 Jul 2010, at 21:42, Bill Burke wrote:
> Ok, Resteasy 2.0.0.GA should be in component-matrix and within our
> public repositories. Thanks for delaying.
>
> Jason T. Greene wrote:
>> Ok, I'll push the tag day until Wednesday to give you more time since
>> this is the last planned milestone before CR. That we you can get better
>> feedback from the community.
>>
>> On 7/13/10 10:42 AM, Bill Burke wrote:
>>> Can you wait until Tues/Wednesday? Resteasy 2.0-RC1 just went out
>>> yesterday. I'm giving it a week+ for users to report back on blockers
>>> or quick fixes then release Restasy 2.0.GA on Monday night. But there
>>> should be very little, if any changes from 2.0-RC1.
>>
>>> Also, is there a way to get maven driven integration tests run with the
>>> build? Resteasy integration tests, within resteasy-int/test module,
>>> require a running jboss instance. If its too difficult, no worries.
>>
>> I see ALR answered this in another thread.
>>
>>> Some things you might want to list as far as JAX-RS goes for M4 release:
>>> * complete CDI and EJB integration
>>> * complete scanning integration. No web.xml resteasy specific code
>>> required
>>
>> OK cool. Do you want me to say more? I could put a big blurb in the
>> release notes if you want.
>>
>>> Jason Greene wrote:
>>>> EJB 3.1 finished the main M4 elements, so the plan is to tag on
>>>> Monday. Is that enough time?
>>>>
>>>> On Jul 6, 2010, at 7:49 AM, Bill Burke wrote:
>>>>
>>>>> I just want to know when I need to get Resteasy 2.0 released by. I
can
>>>>> deferr scheduled bugs/features and release ASAP if needed...
>>>>>
>>>>> Carlo de Wolf wrote:
>>>>>> We're currently working through the integration of timers and
async.
>>>>>> Timers is in trunk. With the exception of some calendar
expression
>>>>>> bits
>>>>>> it's working.
>>>>>> Async is coming soon into trunk. Right now local testing is
being
>>>>>> completed.
>>>>>> Both still need thorough monkey proof testing in terms of
>>>>>> functionality,
>>>>>> performance and memory usage.
>>>>>>
>>>>>> I don't mind any component update that does not bring any
regression.
>>>>>>
>>>>>> Carlo
>>>>>>
>>>>>> On 07/03/2010 04:24 AM, Jason Greene wrote:
>>>>>>> It's currently on hold waiting for ejb 3.1 timers and
async
>>>>>>>
>>>>>>> Carlo,
>>>>>>>
>>>>>>> Any update here?
>>>>>>>
>>>>>>> On Jul 2, 2010, at 6:20 PM, Bill Burke wrote:
>>>>>>>
>>>>>>>
>>>>>>>> I want to do another RESTEasy release (2.0.GA) before M4
is
>>>>>>>> released so
>>>>>>>> M4 is up-to-date... ETA on M4?
>>>>>>>>