5.1 Beta1
---------
Code Freeze: March 9th
Release: March 16th
Last I heard the release date was March 10th? Did this move or was the 10th tentative?
The primary/required goal for this release is completion of all
Profile
Service blockers, to facilitate the inclusion of the console:
https://jira.jboss.org/jira/browse/JBAS-6470
All other planned component updates for this release are located
here:
https://jira.jboss.org/jira/browse/JBAS-6156
If one of these subtasks is assigned to you, and you can not complete
this in *2 weeks*, please let me know, so I can reschedule it to CR1.
Also please review the JIRA issues assigned to you and reschedule them
if you can not complete them for this release.
5.1 CR1
-------
Code Freeze: April 6th (Tentative)
Release: April 13th (Tentative)
The primary/required goal is inclusion of the embedded console. A
secondary goal is including JBM 2 as either an optional or main JMS
provider. These dates could slip a few more weeks depending on the
console timeline.
We're planning the console release right now, but I would expect a move to the right
of several weeks from the dates you have above (assuming the Beta1 dates don't
change). We should have a firm console schedule early next week.
All major component upgrades need to be completed and in CR quality
for
this release (with the exception of tech preview features.
5.1 GA
------
Code Freeze: May 4th (Tentative)
Release: May 18th (Tentative)
The primary/required goal is of course all tests (including TCK)
cleared
and all assigned bugs resolved.
Any questions, feedback?
--
Jason T. Greene
JBoss, a division of Red Hat
_______________________________________________
jboss-development mailing list
jboss-development(a)lists.jboss.org
https://lists.jboss.org/mailman/listinfo/jboss-development