4.2.2.GA release is on cards and still Installer for 4.2.1.GA is not
out. I think it makes lot of sense to keep Installer and JBoss AS
release dates as close as possible (irrespective of components included
in installer) otherwise we are just wasting our efforts for unreleased
Installers.
Regards,
Amit.
Dimitris Andreadis wrote:
It is not our #1 priority but the clock is ticking for the next bug
fixing release for AS 4.2, targeted for mid October.
The cut-off date for work on Branch_4_2 is *Sep/21st*.
After that, only testsuite fixes, until the release date.
Please, take a look at the scheduled tasks:
http://jira.jboss.com/jira/secure/IssueNavigator.jspa?reset=true&mode...
- unschedule/reschedule tasks that won't be fixed now
- make sure we haven't missed some important task for 4.2.2.GA
- mark as critical the important ones
- work on the tasks you are assigned
For this release we are dependending on remoting 2.2.2.GA and JBossWeb
2.0.1.GA, so the respective owners, please follow up with delivery
estimates.
Related testsuites:
http://hudson.jboss.org/hudson/job/JBoss-AS-4.2.x-TestSuite-sun15/
http://hudson.jboss.org/hudson/job/JBoss-AS-4.2.x-TestSuite-jrockit15/
http://hudson.jboss.org/hudson/job/JBoss-AS-4.2.x-CompatibilityMatrix/
Internal Hudson
(
http://dev45.qa.atl.jboss.com:8585/hudson/view/JBoss%20AS/)
For any issue, let me know.
Thanks
/D