At what phase/time-period would tools requirements be discussed ?
Last time we said early april but with this schedule is there any room
for that ?
/max
Due to recent changes in the EAP5 schedule, we have had to
significantly pull in our community dates. The new CR1 and GA dates
are as follows:
CR1
---
Code/Component Freeze : April 20th
Final Console Inclusion : April 22nd
Release : April 27th
GA
--
Code/Component Freeze : May 11th
Release : May 25th
There is now only 1 goal, and that is meeting our dates with a working
console.
This also means profile service work is the priority:
https://jira.jboss.org/jira/browse/JBAS-6620
All other updates are a nice to have, and if you want them included in
5.1, they need to be done as early as possible.